Rapid Impact Compaction at Duffin Meadows Funeral Centre
We recently reached an important milestone on the Duffin Meadows Funeral Centre groundworks.
After reviewing the geotechnical report during our preconstruction investigations, we learned the soil could not support the planned 21,000-square-foot building with conventional footings and foundations. Understanding Mount Pleasant Group’s priorities, including minimizing the carbon footprint of construction activities, Dalton’s QS team led an extensive value engineering exercise to identify suitable alternatives, including a relatively new technique, Rapid Impact Compaction (RIC).

RIC improves ground conditions without adding materials such as stone or concrete. This makes it one of the most environmentally sustainable and cost-effective ground improvement techniques available. We partnered with geotechnical specialist Menard Canada to complete this important step.
The key benefits for the Duffin Meadows project included:
Accelerating the foundation installation schedule ahead of winter and enabling a quicker transition to subsequent construction phases;
Reducing overall cost per cubic metre compared to traditional methods, since no removal is required below the slab or footings;
Minimizing machinery and logistics overhead, thereby lowering the project’s operational carbon footprint.
We are proud of our experienced team, which continually expands its expertise and embraces innovative methods to achieve our client’s Definition of Success.
Choosing RIC for ground improvement proved the right decision. The work finished ahead of schedule, met our quality expectations, and caused minimal disruption for cemetery visitors and neighbouring residents.